The Government of Greenland was due to file its defence in the Kuannersuit case on 27 October 2026. Instead, it has requested the High Court of Greenland for seven more weeks to do so. The dispute has been running for more than four and a half years, and the case has been before the High Court of Greenland since May 2024. The court has already extended the deadline once.
On the very day of the deadline, Greenland’s lawyers requested the court for a further extension of nothing less than seven weeks. The reason given is that the defence needs to be translated from Danish into Greenlandic so that the Government of Greenland can approve it. The lawyers have confirmed the defence is ready. Allegedly, they just need this “approval process” to be able to file it.
ETM has opposed this illegitimate and – frankly grotesque – request for extension of time for several reasons. It should hardly come as a surprise. The government’s lawyers are – measured by headcount – Denmark’s largest law firm, and they must be presumed capable of structuring the relevant work processes to obtain client approval in time, especially when they have had years to do it.
It is the Government of Greenland’s own defence, and its lawyers must have known from the outset that it would need to be translated into Greenlandic for the Government of Greenland to approve it. Danish is an official court language and public language in Greenland as well, and so presumably all involved also understand Danish.
In addition to its pattern of repeated procrastination of the legal proceedings, the Government of Greenland and their lawyers also seem to prefer delaying things so that they file their pleadings in the case right before public holiday periods – this time shortly before Christmas. The thinking must be that they intend to cause as much logistical challenge as possible for ETM to coordinate initial work in reviewing and responding to what is filed.
In opposing this latest delay tactic from the Government of Greenland, ETM has insisted that any delay must not push back the main hearing. The court has indicated its availability for a hearing from around September 2027 until the end of June 2028.
Securing procedural fairness and bringing the case to an efficient conclusion ought to be in Greenland’s own interest. Much of the future investment in Greenland’s mining industry is expected to come from abroad, and investors pay close attention to how disputes are handled. ETM’s case concerns whether the rule of law has been respected in the handling of what is currently Greenland’s largest mining project. How efficiently such a case is dealt with by the courts matters for investor confidence in Greenland. Yet, in ETM’s view, the Government of Greenland increasingly appears more interested in postponing the case than in having it heard on the merits.
The timing is striking for another reason as well: At this very moment, a delegation from Greenland’s Ministry of Business and Mineral Resources is in Sydney at the International Mining and Resources Conference (IMARC) to attract more investment to Greenland’s mining sector. Meanwhile, ETM, a long-standing investor that has spent more than DKK 1 billion on Kuannersuit since 2007, is still waiting to have its rightful exploitation issued and for the Government of Greenland to answer its case in the pending court proceedings.
Daniel Mamadou, CEO of ETM, said:
“It is embarrassing that the Government of Greenland, after more than four and a half years, still cannot present its defence on time. They have known about this specific deadline for months, the court has already given them extra time, and they only told us on the day itself.
That the lawyers need to translate the defence into Greenlandic so their client can approve it is not an unexpected obstacle. It is something any lawyer acting for the Government of Greenland would plan for. When it is used as a reason for yet another delay, it is hard to see it as anything other than another delay tactic. That is why we have objected, and we expect the court to reject this obvious attempt to substantially delay things further.
This is no longer about procedure. It is harassment, and we see it as an attempt to drive ETM out of Greenland by dragging the case out for as long as possible. We have presented our case and we are ready to have it heard. The question is why the Government of Greenland is not.
It also sends a clear signal to other investors in Greenland’s mining industry. If this is how a company is treated after more than a decade of investment and four and a half years of dispute, every investor considering Greenland should take note.”
About Energy Transition Minerals Ltd
Energy Transition Minerals Ltd (ASX: ETM) is an international company focused on the responsible development of rare earth and specialty metals projects that support the transition to green energy.